In Nevada, a lien claimant must record a notice of lien with the county recorder within 90 days after the latest of completion of the work of improvement, its last delivery of material or equipment, or its last work, or within 40 days after a valid notice of completion is recorded. On the construction, alteration or repair of a single-family or multifamily residence, a lien claimant other than a laborer must serve a 15-day notice of intent to lien on the owner and the reputed prime contractor before recording, which extends the recording deadline by 15 days. A prime contractor who contracts directly with the owner does not have to give the notice of right to lien. The lien stops binding the property 6 months after it is recorded unless a court action to enforce it is commenced within that time or a recorded written extension is signed. A subcontractor or supplier often has different notice requirements and deadlines. This is NRS 108.226, 108.245, 108.233.

WhatNevada
Deadline to file the lien90 days after completion or last work
Who this deadline is forA contractor hired directly by the owner

Source

NRS 108.226, 108.245, 108.233

Read the statute in the Nevada Revised Statutes (Nevada Legislature): leg.state.nv.us.

Checked against the statute on November 13, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed and the amount still owed are on file when a lien deadline is counted.

Guides on this rule

Compare this rule in every state

More Nevada rules

The same question in other states

Related