What is the deadline to file a mechanic’s lien in South Dakota?

In South Dakota, a contractor must file a lien statement with the county register of deeds within 120 days after doing the last work or furnishing the last materials, or the lien ceases. Before filing, the contractor must mail a copy of the lien statement to the property owner by registered or certified mail and attach the post office receipt to the statement. No preliminary notice is required of a contractor who contracted with the owner; filing a notice of project commencement is optional. The lien must be asserted by complaint or answer within six years after the date of the last item of the claim in the filed lien statement. If the owner, the owner’s agent or the contractor serves a written demand to sue, suit must be commenced within 30 days after service or the lien is forfeited. A subcontractor or supplier often has different notice requirements and deadlines. This is SDCL §§ 44-9-15, 44-9-17, 44-9-24, 44-9-26, 44-9-50.

WhatSouth Dakota
Deadline to file the lien120 days after the last work
Who this deadline is forA contractor hired directly by the owner

Source

SDCL §§ 44-9-15, 44-9-17, 44-9-24, 44-9-26, 44-9-50

Read the statute in the South Dakota Codified Laws (South Dakota Legislature): sdlegislature.gov.

Checked against the statute on November 13, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed and the amount still owed are on file when a lien deadline is counted.

Guides on this rule

Compare this rule in every state

More South Dakota rules

The same question in other states

Related