What does Utah’s prompt payment law require on private construction?
In Utah, a contractor paid for billed work must pay its subcontractors and suppliers their share within 30 days after receiving the funds or after payment is due under the billing, whichever is later, unless the contract says otherwise, or owe 1% a month interest plus collection costs and attorney fees. The construction trades statute sets no deadline for an owner’s progress payments; it makes unpaid construction funds payable to the contractor as provided in Section 13-8-5, which governs retention. On nonresidential commercial or industrial projects, retention may not exceed 5% of any payment and must be released within 45 days after the later of the contractor’s billing statement, a certificate of occupancy or final acceptance notice, permitted occupancy, or the contractor’s acceptance of final pay quantities, and a contractor must pay each subcontractor its share of retention within 10 days of receiving it. An owner or contractor who knowingly and wrongfully withholds retention owes a charge of 2% a month on top of any interest due. From January 1, 2027, H.B. 40 (2026) moves the subcontractor payment rule to Section 58-55-209 with the same 30-day deadline and 1% monthly interest. A written contract can set its own payment terms where the statute allows. This is Utah Code §§ 58-55-602, 58-55-603, 13-8-5.
| What | Utah |
|---|---|
| Payment deadline | Subcontractor paid within 30 days; 1% a month |
| Who this covers | Private construction, not only public works |
What the statute says
“… the contractor fails to pay for work performed by subcontractors or suppliers within 30 consecutive days after receiving construction funds from the owner or another contractor for work performed and billed …”
Quoted word for word from the section’s text.
Source
Utah Code §§ 58-55-602, 58-55-603, 13-8-5
Read the statute in the Utah Code (Utah Legislature): le.utah.gov.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Prompt Payment Laws by State for Private Construction — How many days an owner has to pay a contractor on private construction, in each of the 36 jurisdictions with a prompt payment statute.
Compare this rule in every state
More Utah rules
- How long does a landlord have to return a security deposit in Utah?
- How many days does a tenant get to pay late rent in Utah?
- How much notice must a landlord give to end a tenancy in Utah?
- What are squatters’ rights in Utah?
- Is there rent control in Utah?
- Can a landlord refuse a Section 8 voucher in Utah?
- Can a domestic violence victim end a lease early in Utah?
- What happens if a tenant breaks a lease in Utah?
- What can a landlord do with a tenant’s belongings left behind in Utah?
- Do HVAC contractors need a license in Utah?
- Do you need a general contractor license in Utah?
- Do you need a license to do electrical work in Utah?
- Do you need a license to work as a plumber in Utah?
- Can you use a transfer-on-death deed in Utah?
- How does joint tenancy with right of survivorship work in Utah?
- What is the deadline to file a mechanic’s lien in Utah?
- Does a home seller have to disclose the property’s condition in Utah?
- How long does a homeowner have to cancel a home improvement contract in Utah?
- Do contractors charge sales tax in Utah?
- Is appliance repair taxable in Utah?
- Every Utah rule on one page
The same question in other states
- Alabama
- Arizona
- California
- Connecticut
- Delaware
- District of Columbia
- Florida
- Georgia
- Hawaii
- Illinois
- Kansas
- Kentucky