What does Minnesota’s prompt payment law require on private construction?
In Minnesota, a prime contractor and every subcontractor pay their subcontractors and suppliers undisputed amounts within ten days of being paid, late undisputed amounts carry 1.5% a month interest, and unless the contract says otherwise an owner makes progress payments monthly as the work progresses. The minimum monthly interest penalty on an unpaid balance of $100 or more is $10, and a party who wins a civil action to collect the interest must be awarded its costs and disbursements, including attorney fees. If an undisputed payment is not received within ten days, a contractor or subcontractor of any tier may suspend work until it is received. Retainage may not exceed five percent, the owner must release it no later than 60 days after substantial completion, and a contractor must pay remaining retainage to its subcontractors within ten days after receiving it; these retainage and progress payment rules do not apply to public agencies. The statute sets no fixed number of days for an owner to pay a contractor. A written contract can set its own payment terms where the statute allows. This is Minn. Stat. §§ 337.10, 337.01.
| What | Minnesota |
|---|---|
| Payment deadline | Subs paid within 10 days; 1.5% a month interest |
| Who this covers | Private construction, not only public works |
What the statute says
“A building and construction contract shall be deemed to require the prime contractor and all subcontractors to promptly pay any subcontractor or material supplier contract within ten days of receipt by the party responsible for payment …”
Quoted word for word from the section’s text.
Source
Read the statute in the Minnesota Statutes (Office of the Revisor of Statutes): revisor.mn.gov.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Prompt Payment Laws by State for Private Construction — How many days an owner has to pay a contractor on private construction, in each of the 36 jurisdictions with a prompt payment statute.
Compare this rule in every state
More Minnesota rules
- Does a landlord have to pay interest on a security deposit in Minnesota?
- How long does a landlord have to return a security deposit in Minnesota?
- How many days does a tenant get to pay late rent in Minnesota?
- How much notice does a landlord have to give before raising the rent in Minnesota?
- How much notice must a landlord give to end a tenancy in Minnesota?
- How much can a landlord charge for a late rent fee in Minnesota?
- Can a landlord change the locks to force a tenant out in Minnesota?
- How long does a tenant have to respond to an eviction case in Minnesota?
- What are squatters’ rights in Minnesota?
- What are the steps to evict a tenant for unpaid rent in Minnesota?
- Is there rent control in Minnesota?
- Can a landlord refuse a Section 8 voucher in Minnesota?
- Can a landlord retaliate against a tenant for complaining in Minnesota?
- Can a tenant withhold rent for repairs in Minnesota?
- Can a domestic violence victim end a lease early in Minnesota?
- What happens if a tenant breaks a lease in Minnesota?
- What can a landlord do with a tenant’s belongings left behind in Minnesota?
- Do you need a general contractor license in Minnesota?
- Do you need a license to do electrical work in Minnesota?
- Do you need a license to work as a plumber in Minnesota?
- Can you use a transfer-on-death deed in Minnesota?
- How does joint tenancy with right of survivorship work in Minnesota?
- What is the deadline to file a mechanic’s lien in Minnesota?
- Does a home seller have to disclose the property’s condition in Minnesota?
- What is the real estate transfer tax in Minnesota?
- How long does a homeowner have to cancel a home improvement contract in Minnesota?
- Do contractors charge sales tax in Minnesota?
- Every Minnesota rule on one page
The same question in other states
- Alabama
- Arizona
- California
- Connecticut
- Delaware
- District of Columbia
- Florida
- Georgia
- Hawaii
- Illinois
- Kansas
- Kentucky