What are the rules for lien waivers in California?

In California, a lien waiver is void and unenforceable unless it is in substantially one of the four statutory forms (conditional or unconditional, on a progress payment or the final payment), and a contract term that waives another claimant’s lien rights is void until that claimant signs one. A conditional waiver releases the owner, construction lender or payment bond surety only if there is evidence of payment, such as the claimant’s endorsement on a check the bank has paid or a written acknowledgment of payment. Any other oral or written statement that purports to waive a lien is void unless the claimant has actually been paid in full. This is Cal. Civ. Code §§ 8122, 8124, 8126, 8132, 8134, 8136, 8138.

WhatCalifornia
Lien waiversStatutory conditional and unconditional forms
Kind of ruleThe statute prescribes the waiver forms

What the statute says

“… a single payee check or joint payee check is given in exchange for the waiver and release, the waiver and release shall be null, void, and unenforceable unless it is in substantially the following form …”

Quoted word for word from the section’s text.

Source

Cal. Civ. Code §§ 8122, 8124, 8126, 8132, 8134, 8136, 8138

Read the statute in the California Codes (California Legislative Information): leginfo.legislature.ca.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More California rules

The same question in other states

Related