What are the rules for lien waivers in Georgia?

In Georgia, a lien waiver is enforceable only on the statutory interim-payment or final-payment form, a waiver made before the labor, services or materials are furnished is void, and a signed waiver takes effect no later than 90 days after signing, even if unpaid, unless the claimant files an affidavit of nonpayment within that time. The forms must be in at least 12-point type, and a form that leaves out its statutory notice is unenforceable as a waiver. A waiver given to settle a bona fide dispute over work already furnished, and an advance subordination of lien rights, remain enforceable. This is O.C.G.A. § 44-14-366.

WhatGeorgia
Lien waiversStatutory interim and final forms; advance waivers void
Kind of ruleThe statute prescribes the waiver forms

What the statute says

“A right to claim a lien or to claim upon a bond may not be waived in advance of furnishing of labor, services, or materials.”

Quoted word for word from the section’s text.

Source

O.C.G.A. § 44-14-366

Read the statute in the Official Code of Georgia (Georgia General Assembly): legis.ga.gov.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Georgia rules

The same question in other states

Related