What are the rules for lien waivers in Connecticut?

In Connecticut, a contract clause or periodic lien waiver that gives up the right to claim a mechanic’s lien or a payment bond claim for services, labor or materials not yet performed and paid for is void. The rule does not prohibit subordinating a mechanic’s lien to a mortgage or security interest, or enforcing an agreement to do so. It covers private construction contracts other than public works, HUD-funded projects, contracts of $25,000 or less, and buildings for residential occupancy with four or fewer units. This is Conn. Gen. Stat. §§ 42-158i, 42-158l.

WhatConnecticut
Lien waiversAdvance waivers are void
Kind of ruleAdvance or contract waivers are limited

What the statute says

“… (1) claim a mechanic’s lien, or (2) make a claim against a payment bond, for services, labor or materials which have not yet been performed and paid for shall be void and of no effect …”

Quoted word for word from the section’s text.

Source

Conn. Gen. Stat. §§ 42-158i, 42-158l

Read the statute in the Connecticut General Statutes (Connecticut General Assembly): cga.ct.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Connecticut rules

The same question in other states

Related