What are the rules for lien waivers in Colorado?

In Colorado, an agreement to waive mechanic’s lien rights binds only the parties to that contract, and it must include a statement by the person waiving that all debts to third parties for the goods or services it covers have been paid or will be timely paid. This is C.R.S. § 38-22-119.

WhatColorado
Lien waiversWaivers bind only the parties; must say debts are paid
Kind of ruleAdvance or contract waivers are limited

What the statute says

“No agreement to waive, abandon, or refrain from enforcing any lien provided for by this article shall be binding except as between the parties to such contract.”

Quoted word for word from the section’s text.

Source

C.R.S. § 38-22-119

Read the statute in the Colorado Revised Statutes (Colorado General Assembly): leg.colorado.gov.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Colorado rules

The same question in other states

Related