What are the rules for lien waivers?

It depends on the state. Seayora holds a published statute for 32 states and the District of Columbia. The table below gives the figure for each, with the statute it comes from.

Lien waivers, state by state

StateLien waiversSource
AlaskaWaivers cannot cover later work; workers cannot waiveAlaska Stat. §§ 34.35.117, 34.35.120
ArizonaStatutory conditional and unconditional formsA.R.S. § 33-1008
CaliforniaStatutory conditional and unconditional formsCal. Civ. Code §§ 8122, 8124, 8126, 8132, 8134, 8136, 8138
ColoradoWaivers bind only the parties; must say debts are paidC.R.S. § 38-22-119
ConnecticutAdvance waivers are voidConn. Gen. Stat. §§ 42-158i, 42-158l
DelawareAdvance waivers are void25 Del. C. § 2706
District of ColumbiaPay-when-paid terms cannot waive a sub’s lien rightsD.C. Code §§ 27A-104, 40-303.02
FloridaStatutory forms; advance waivers are unenforceableFla. Stat. § 713.20
GeorgiaStatutory interim and final forms; advance waivers voidO.C.G.A. § 44-14-366
IllinoisWaivers given to win a contract are unenforceable770 ILCS 60/1(c)-(d)
IndianaWaivers required before payment are voidInd. Code §§ 32-28-3-1(e)-(f), 32-28-3-16
KansasLien waivers only for payment actually receivedK.S.A. 16-1803(b)(2), 16-1807
KentuckyContract lien waivers void, except for progress paymentsKRS 371.405(2)(b), 371.425
MarylandSubcontract waivers of lien rights in advance are voidMd. Code, Real Prop. § 9-113
MassachusettsAdvance waivers void; statutory partial waiver formM.G.L. c. 254, § 32
MichiganStatutory conditional and unconditional waiver formsMCL 570.1115
MinnesotaWaivers required before payment are voidMinn. Stat. § 337.10, subd. 2
MississippiStatutory interim and final forms; advance waivers voidMiss. Code Ann. §§ 85-7-419, 85-7-433
MissouriWaivers given to win a contract are unenforceableMo. Rev. Stat. § 429.005
MontanaContracts may not require a waiver before paymentMont. Code Ann. § 28-2-723
NevadaStatutory conditional and unconditional formsNRS 108.2457
New JerseyWaivers void unless given for payment actually receivedN.J.S.A. 2A:44A-38
New YorkAdvance waivers are void; waive only at or after paymentN.Y. Lien Law § 34
North CarolinaWaivers given to win the contract are unenforceableN.C. Gen. Stat. § 44A-12
PennsylvaniaNonresidential waivers void unless for payment received49 P.S. §§ 1401, 1201
Rhode IslandAdvance lien waivers are void; waivers at payment are OKR.I. Gen. Laws § 34-28-1
TennesseeContract waivers of lien rights are voidTenn. Code § 66-11-124
TexasStatutory conditional and unconditional formsTex. Prop. Code §§ 53.281, 53.282, 53.283, 53.284, 53.286
UtahContract waivers void; waivers count only once paidUtah Code §§ 38-1a-105, 38-1a-802
VermontAdvance lien waivers are unenforceable9 V.S.A. § 1921
VirginiaAdvance lien waivers in a contract are voidVa. Code § 43-3
WisconsinContract terms requiring waivers before payment are voidWis. Stat. §§ 779.135, 779.05
WyomingStatutory lien waiver form, acknowledged before a notaryWyo. Stat. § 29-10-101

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

Only states where Seayora holds a published statute appear above. Where no statute is recorded, no figure is shown rather than a guess.

The answer in full, for the biggest rental markets

What are the rules for lien waivers in California?

In California, a lien waiver is void and unenforceable unless it is in substantially one of the four statutory forms (conditional or unconditional, on a progress payment or the final payment), and a contract term that waives another claimant’s lien rights is void until that claimant signs one. A conditional waiver releases the owner, construction lender or payment bond surety only if there is evidence of payment, such as the claimant’s endorsement on a check the bank has paid or a written acknowledgment of payment. Any other oral or written statement that purports to waive a lien is void unless the claimant has actually been paid in full. This is Cal. Civ. Code §§ 8122, 8124, 8126, 8132, 8134, 8136, 8138.

More on California

What are the rules for lien waivers in Texas?

In Texas, a lien waiver is enforceable only if it substantially follows one of four statutory forms (conditional or unconditional, on a progress or final payment), and nobody may require an unconditional waiver before the payment is received. A waiver and release of a lien or payment bond claim is unenforceable unless it substantially complies with the applicable statutory form: a conditional or unconditional waiver and release on progress payment or on final payment. It is effective only if it is signed by the claimant or the claimant’s authorized agent and, for a conditional release, evidence of payment to the claimant exists. A person may not require a claimant to sign an unconditional waiver and release unless the claimant received payment in that amount in good and sufficient funds. Any contract or agreement purporting to waive the right to file or enforce a lien is void as against public policy, except a written waiver in an original contract or subcontract for a single-family house, townhouse or duplex made before labor or materials are provided, and that exception does not apply to a person who supplies only material. This is Tex. Prop. Code §§ 53.281, 53.282, 53.283, 53.284, 53.286.

More on Texas

What are the rules for lien waivers in Florida?

In Florida, a right to claim a construction lien cannot be waived in advance, a waiver covers only labor, services or materials already furnished, and no one may require a lienor to sign a waiver different from the statutory progress-payment and final-payment forms. A lienor who signs a waiver in exchange for a check may condition the waiver on payment of the check. A waiver that is not substantially similar to the statutory forms is still enforceable according to its terms. This is Fla. Stat. § 713.20.

More on Florida

What are the rules for lien waivers in New York?

In New York, any contract or agreement that waives the right to file or enforce a mechanic’s lien is void, although a written waiver may be required when or after payment is made. Any contract, agreement or understanding by which the right to file or enforce a mechanic’s lien is waived is void as against public policy and wholly unenforceable. The rule does not bar requiring a written waiver signed simultaneously with or after payment for the labor or materials, or a written agreement to subordinate, release or satisfy a lien made after a notice of lien has been filed. The statute prescribes no waiver form. This is N.Y. Lien Law § 34.

More on New York

What are the rules for lien waivers in Pennsylvania?

In Pennsylvania, on a nonresidential building a contractor’s or subcontractor’s waiver of lien rights is void unless given in exchange for payment and only to the extent the payment is actually received, while lien rights on residential property may be waived in a signed writing. On nonresidential buildings, a waiver of lien rights by a contractor is against public policy, unlawful and void unless given in consideration for payment for the work, services, materials or equipment provided, and only to the extent that payment is actually received. The same rule applies to a subcontractor’s waiver unless the contractor has posted a bond guaranteeing payment for labor and materials. On residential property, a contractor or subcontractor may waive the right to file a claim by a signed written instrument or by conduct that equitably estops it from filing. Residential property means, in general, property with a residential building not more than three stories high, not counting a basement. The law prescribes no waiver form. This is 49 P.S. §§ 1401, 1201.

More on Pennsylvania

What are the rules for lien waivers in Illinois?

In Illinois, an agreement to waive or subordinate mechanics lien rights made in anticipation of and in consideration for the awarding of a contract or subcontract is against public policy and unenforceable. An agreement to waive any right to enforce or claim a lien under the Mechanics Lien Act, or to subordinate the lien, made in anticipation of and in consideration for the awarding of a contract or subcontract to improve real property is against public policy and unenforceable. The rule does not prohibit a release of lien under subsection (b) of Section 35, or an agreement to subordinate a mechanics lien to a construction loan mortgage made after more than 50% of the loan has been disbursed to fund improvements. Taking additional security is not a waiver of a lien right unless the parties expressly agree to a waiver the Act does not prohibit. This is 770 ILCS 60/1(c)-(d).

More on Illinois

What are the rules for lien waivers in Georgia?

In Georgia, a lien waiver is enforceable only on the statutory interim-payment or final-payment form, a waiver made before the labor, services or materials are furnished is void, and a signed waiver takes effect no later than 90 days after signing, even if unpaid, unless the claimant files an affidavit of nonpayment within that time. The forms must be in at least 12-point type, and a form that leaves out its statutory notice is unenforceable as a waiver. A waiver given to settle a bona fide dispute over work already furnished, and an advance subordination of lien rights, remain enforceable. This is O.C.G.A. § 44-14-366.

More on Georgia

What are the rules for lien waivers in North Carolina?

In North Carolina, an agreement to waive the right to file a claim of lien, made in anticipation of and in consideration for being awarded the contract, is against public policy and unenforceable. An agreement to waive the right to file a claim of lien on real property, or to serve a notice of claim of lien upon funds, that is made in anticipation of and in consideration for the awarding of a contract to improve real property is against public policy and unenforceable. The rule does not prohibit the subordination or release of a lien, and the statute prescribes no waiver form. This is N.C. Gen. Stat. § 44A-12.

More on North Carolina

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Other rules compared across states

Every rule for one state

Related