How much retainage can be held on private construction?

It depends on the state. Seayora holds a published statute for 34 states and the District of Columbia. The table below gives the figure for each, with the statute it comes from.

Retainage, state by state

StateRetainageSource
AlabamaCapped at 10%, none after 50%; released within 60 daysAla. Code §§ 8-29-3, 8-29-7
ArizonaReleased 7 days after approval at substantial completionA.R.S. §§ 32-1182, 32-1183, 32-1188
CaliforniaCapped at 5%; released within 45 days of completionCal. Civ. Code §§ 8811, 8812, 8814, 8818
ColoradoCapped at 5% on contracts of $150,000 or moreC.R.S. §§ 38-46-102, 38-46-103
ConnecticutCapped at 5%; paid within 30 days of final completionConn. Gen. Stat. §§ 42-158i, 42-158k, 42-158p
District of ColumbiaUndisputed retainage paid within 7 days of contract dateD.C. Code §§ 27A-101, 27A-102, 27A-103, 27A-104, 27A-106
FloridaReleased within 14 days after completion and punch listFla. Stat. § 715.12
GeorgiaSubs’ retainage passed through within 10 days of receiptO.C.G.A. §§ 13-11-5, 13-11-6, 13-11-10
IdahoCapped at 5%; released within 35 days of final completionIdaho Code § 29-115
IllinoisCapped at 10%, then 5% once the job is 50% complete815 ILCS 603/5(b), 603/20
Kansas5% cap (10% at most); released 30 days after completionK.S.A. 16-1804, 16-1807
Kentucky10%, then 5% past 50%; released 30 days after completionKRS 371.410, 371.425
LouisianaNo cap; $50,000+ contracts escrow retainage with interestLa. R.S. 9:4857, 9:4858
MaineNo cap; released within 30 days after final acceptance10 M.R.S. §§ 1111, 1116, 1118
Maryland5% cap if fully bonded; released 90 days after completionMd. Code, Real Prop. §§ 9-304, 9-305
MassachusettsCapped at 5% of each progress payment ($3M+ projects)M.G.L. c. 149, § 29F
MinnesotaCapped at 5%; released 60 days after substantial completionMinn. Stat. § 337.10, subd. 4
MississippiCapped at 5%; released 60 days after final completionMiss. Code Ann. § 87-9-3
MissouriCapped at 10%; released 30 days after completionMo. Rev. Stat. §§ 436.303, 436.324, 436.336
MontanaCapped at 5%; released on acceptance of each priced portionMont. Code Ann. §§ 28-2-2110, 28-2-2101, 28-2-2107
NebraskaCapped at 10%, 5% after half done; released in 45 daysNeb. Rev. Stat. §§ 45-1204, 45-1203, 45-1202, 45-1207
NevadaCapped at 5% of each payment; due 30 days after useNRS 624.609, 624.620, 624.624, 624.622
New JerseyNo cap; retainage paid 30 days after an approved billingN.J.S.A. 2A:30A-2, 2A:30A-1
New MexicoNo retainage allowed; balance due 10 days after completionN.M. Stat. Ann. §§ 57-28-5, 57-28-8, 57-28-2, 57-28-3
New YorkCapped at 5%; released within 30 days of final approvalN.Y. Gen. Bus. Law §§ 756, 756-c, 757
North CarolinaSub retainage capped at the owner’s initial percentageN.C. Gen. Stat. §§ 22C-4, 22C-3, 22C-5, 22C-6
North DakotaCapped at 10% until half complete, then no more retainageN.D. Cent. Code § 43-07-23
OhioNo cap; subs’ retainage paid within 10 days of receiptOhio Rev. Code § 4113.61
OregonCapped at 5%; 1% a month interest on late final paymentORS 701.420, 701.410, 701.440
PennsylvaniaNo cap; released within 30 days of final acceptance73 P.S. §§ 509, 503, 505
Rhode IslandCapped at 5% of each progress paymentR.I. Gen. Laws §§ 37-12-10.1, 5-65-1
TennesseeCapped at 5%; released within 90 days of completionTenn. Code §§ 66-34-103, 66-34-104
UtahCapped at 5%; due within 45 days of billing or occupancyUtah Code § 13-8-5
VermontNo cap; released within 30 days of final acceptance9 V.S.A. § 4005
WashingtonCapped at 5%; 1%/month interest 30 days after acceptanceRCW 60.30.010, 60.30.020, 60.30.030

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

Only states where Seayora holds a published statute appear above. Where no statute is recorded, no figure is shown rather than a guess.

The answer in full, for the biggest rental markets

How much retainage can be held on private construction in California?

In California, retainage on a private work of improvement contracted on or after January 1, 2026 is capped at 5 percent of each payment and of the contract price, and an owner holding retention must pay it to the direct contractor within 45 days after completion of the work. A direct contractor must pay each subcontractor its share within 10 days after receiving a retention payment, and a late retention payment carries a penalty of 2 percent per month. The 5 percent cap does not apply to a residential project that is not mixed-use and does not exceed four stories, or to a subcontractor that was told at bidding that a performance and payment bond would be required and then failed to furnish one. This is Cal. Civ. Code §§ 8811, 8812, 8814, 8818.

More on California

How much retainage can be held on private construction in Florida?

In Florida, an owner may withhold part of each progress payment until substantial completion, but must pay the balance, including the amounts withheld, within 14 days after the project is certified substantially complete, a certificate of occupancy issues or the owner or a tenant takes possession, and the contractor substantially completes the owner’s written punch list. Funds retained past that deadline accrue interest at the rate set in s. 55.03 plus 12 percent a year. If the contract sets no punch list period, the owner has 15 days after the triggering event to give one, and if none is given interest begins 14 days after that event. A contractor or lower-tier party may withdraw retained amounts by depositing U.S. Treasury obligations, Florida bonds or notes, or insured certificates of deposit. The law applies to written contracts entered into after December 31, 1992 for which a construction lien is authorized, and it sets no maximum percentage. This is Fla. Stat. § 715.12.

More on Florida

How much retainage can be held on private construction in New York?

In New York, retainage on a private construction project with an aggregate cost of $150,000 or more may not exceed five percent of the contract sum and is released no later than thirty days after final approval of the work. By mutual agreement an owner may retain no more than five percent of the contract sum as retainage, and a contractor or subcontractor may retain no more than five percent and never more than the owner actually retains. The owner must release retainage to the contractor no later than thirty days after final approval of the work, and a party that fails to release retainage owes interest at one percent per month. A contract provision requiring retainage above five percent of the contract sum is void and unenforceable. The law covers construction contracts on projects with an aggregate cost of $150,000 or more and excludes public works and smaller residential projects, including one-, two- and three-family homes. This is N.Y. Gen. Bus. Law §§ 756, 756-c, 757.

More on New York

How much retainage can be held on private construction in Pennsylvania?

In Pennsylvania, the law sets no retainage percentage, but retainage due on final completion is paid within 30 days after final acceptance of the work and passed down to subcontractors within 14 days after it is received. If payments under a construction contract are subject to retainage, amounts retained and due on final completion must be paid within 30 days after final acceptance of the work. A contractor must pay its subcontractors, and each subcontractor its own subcontractors, the full amount due within 14 days after receiving the retainage. On reaching substantial completion of its own scope, a contractor or subcontractor may obtain release of retainage early by posting a maintenance bond for 120% of the amount held. A party that unreasonably withholds acceptance or fails to pay retainage owes interest at 1% per month, and the parties may not waive the act’s provisions by contract unless the act allows it. The act does not apply to improvements of six or fewer residential units under construction at the same time. This is 73 P.S. §§ 509, 503, 505.

More on Pennsylvania

How much retainage can be held on private construction in Illinois?

In Illinois, a private construction contract may hold back no more than 10% of any payment before the work is 50% complete and no more than 5% after that, except on single-family homes and buildings of 12 or fewer units. Under the Contractor Prompt Payment Act, a construction contract may provide for retainage of up to 10% of any payment made before 50% of the contract is complete. When the contract is 50% complete, retainage withheld must be reduced so that no more than 5% is held, and no more than 5% of any later payment may be held. The Act does not apply to contracts that require the expenditure of public funds or to contracts for single family residences or multiple family residences with 12 or fewer units in a single building. This is 815 ILCS 603/5(b), 603/20.

More on Illinois

How much retainage can be held on private construction in Ohio?

In Ohio, the statute sets no retainage percentage, but a contractor that receives final retainage from the owner pays each subcontractor and supplier its share within ten calendar days, or sooner if their contract says so, or owes eighteen percent interest. A contractor may reduce a subcontractor’s progress payment by any retainage provision in their contract. When the contractor receives final retainage from the owner, it must pay each subcontractor and material supplier its proportion within ten calendar days after receipt, or within any shorter period in their contract, once their work is satisfactory and approved by the owner. A late payment carries interest of eighteen percent per year, and the interest and fee provisions cannot be waived by agreement. The section does not apply to single-, two- or three-family detached dwellings. This is Ohio Rev. Code § 4113.61.

More on Ohio

How much retainage can be held on private construction in Georgia?

In Georgia, a contractor must pass retainage through to its subcontractors within 10 days after receiving it from the owner, and the retainage held from a subcontractor cannot exceed the percentage the owner retains on that subcontractor’s work. The owner may withhold a reasonable amount for retainage, but no more than the percentage set in its contract with the contractor; the law sets no maximum percentage and no deadline for the owner’s release. The pass-through duty applies when the subcontractor’s work in place equals 50 percent of its subcontract value, its work is proceeding satisfactorily, and it provides any reasonable assurances of performance the contractor requires. The chapter does not apply to residential improvements of 12 or fewer units. This is O.C.G.A. §§ 13-11-5, 13-11-6, 13-11-10.

More on Georgia

How much retainage can be held on private construction in North Carolina?

In North Carolina, a contractor may hold back from a subcontractor only a reasonable retainage no greater than the percentage the owner initially retained, and the statute sets no limit on the owner’s own retainage. A contractor must pay a subcontractor within seven days of receiving each periodic or final payment the full amount received for that subcontractor’s work, but may withhold a reasonable amount for retainage not to exceed the initial percentage retained by the owner. Payments delayed more than seven days bear interest at one percent per month. The chapter does not apply to residential contractors or to residential improvements of 12 or fewer units, among other residential exemptions. This is N.C. Gen. Stat. §§ 22C-4, 22C-3, 22C-5, 22C-6.

More on North Carolina

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Other rules compared across states

Every rule for one state

Related