How much retainage can be held on private construction?
It depends on the state. Seayora holds a published statute for 34 states and the District of Columbia. The table below gives the figure for each, with the statute it comes from.
Retainage, state by state
| State | Retainage | Source |
|---|---|---|
| Alabama | Capped at 10%, none after 50%; released within 60 days | Ala. Code §§ 8-29-3, 8-29-7 |
| Arizona | Released 7 days after approval at substantial completion | A.R.S. §§ 32-1182, 32-1183, 32-1188 |
| California | Capped at 5%; released within 45 days of completion | Cal. Civ. Code §§ 8811, 8812, 8814, 8818 |
| Colorado | Capped at 5% on contracts of $150,000 or more | C.R.S. §§ 38-46-102, 38-46-103 |
| Connecticut | Capped at 5%; paid within 30 days of final completion | Conn. Gen. Stat. §§ 42-158i, 42-158k, 42-158p |
| District of Columbia | Undisputed retainage paid within 7 days of contract date | D.C. Code §§ 27A-101, 27A-102, 27A-103, 27A-104, 27A-106 |
| Florida | Released within 14 days after completion and punch list | Fla. Stat. § 715.12 |
| Georgia | Subs’ retainage passed through within 10 days of receipt | O.C.G.A. §§ 13-11-5, 13-11-6, 13-11-10 |
| Idaho | Capped at 5%; released within 35 days of final completion | Idaho Code § 29-115 |
| Illinois | Capped at 10%, then 5% once the job is 50% complete | 815 ILCS 603/5(b), 603/20 |
| Kansas | 5% cap (10% at most); released 30 days after completion | K.S.A. 16-1804, 16-1807 |
| Kentucky | 10%, then 5% past 50%; released 30 days after completion | KRS 371.410, 371.425 |
| Louisiana | No cap; $50,000+ contracts escrow retainage with interest | La. R.S. 9:4857, 9:4858 |
| Maine | No cap; released within 30 days after final acceptance | 10 M.R.S. §§ 1111, 1116, 1118 |
| Maryland | 5% cap if fully bonded; released 90 days after completion | Md. Code, Real Prop. §§ 9-304, 9-305 |
| Massachusetts | Capped at 5% of each progress payment ($3M+ projects) | M.G.L. c. 149, § 29F |
| Minnesota | Capped at 5%; released 60 days after substantial completion | Minn. Stat. § 337.10, subd. 4 |
| Mississippi | Capped at 5%; released 60 days after final completion | Miss. Code Ann. § 87-9-3 |
| Missouri | Capped at 10%; released 30 days after completion | Mo. Rev. Stat. §§ 436.303, 436.324, 436.336 |
| Montana | Capped at 5%; released on acceptance of each priced portion | Mont. Code Ann. §§ 28-2-2110, 28-2-2101, 28-2-2107 |
| Nebraska | Capped at 10%, 5% after half done; released in 45 days | Neb. Rev. Stat. §§ 45-1204, 45-1203, 45-1202, 45-1207 |
| Nevada | Capped at 5% of each payment; due 30 days after use | NRS 624.609, 624.620, 624.624, 624.622 |
| New Jersey | No cap; retainage paid 30 days after an approved billing | N.J.S.A. 2A:30A-2, 2A:30A-1 |
| New Mexico | No retainage allowed; balance due 10 days after completion | N.M. Stat. Ann. §§ 57-28-5, 57-28-8, 57-28-2, 57-28-3 |
| New York | Capped at 5%; released within 30 days of final approval | N.Y. Gen. Bus. Law §§ 756, 756-c, 757 |
| North Carolina | Sub retainage capped at the owner’s initial percentage | N.C. Gen. Stat. §§ 22C-4, 22C-3, 22C-5, 22C-6 |
| North Dakota | Capped at 10% until half complete, then no more retainage | N.D. Cent. Code § 43-07-23 |
| Ohio | No cap; subs’ retainage paid within 10 days of receipt | Ohio Rev. Code § 4113.61 |
| Oregon | Capped at 5%; 1% a month interest on late final payment | ORS 701.420, 701.410, 701.440 |
| Pennsylvania | No cap; released within 30 days of final acceptance | 73 P.S. §§ 509, 503, 505 |
| Rhode Island | Capped at 5% of each progress payment | R.I. Gen. Laws §§ 37-12-10.1, 5-65-1 |
| Tennessee | Capped at 5%; released within 90 days of completion | Tenn. Code §§ 66-34-103, 66-34-104 |
| Utah | Capped at 5%; due within 45 days of billing or occupancy | Utah Code § 13-8-5 |
| Vermont | No cap; released within 30 days of final acceptance | 9 V.S.A. § 4005 |
| Washington | Capped at 5%; 1%/month interest 30 days after acceptance | RCW 60.30.010, 60.30.020, 60.30.030 |
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
Only states where Seayora holds a published statute appear above. Where no statute is recorded, no figure is shown rather than a guess.
The answer in full, for the biggest rental markets
How much retainage can be held on private construction in California?
In California, retainage on a private work of improvement contracted on or after January 1, 2026 is capped at 5 percent of each payment and of the contract price, and an owner holding retention must pay it to the direct contractor within 45 days after completion of the work. A direct contractor must pay each subcontractor its share within 10 days after receiving a retention payment, and a late retention payment carries a penalty of 2 percent per month. The 5 percent cap does not apply to a residential project that is not mixed-use and does not exceed four stories, or to a subcontractor that was told at bidding that a performance and payment bond would be required and then failed to furnish one. This is Cal. Civ. Code §§ 8811, 8812, 8814, 8818.
How much retainage can be held on private construction in Florida?
In Florida, an owner may withhold part of each progress payment until substantial completion, but must pay the balance, including the amounts withheld, within 14 days after the project is certified substantially complete, a certificate of occupancy issues or the owner or a tenant takes possession, and the contractor substantially completes the owner’s written punch list. Funds retained past that deadline accrue interest at the rate set in s. 55.03 plus 12 percent a year. If the contract sets no punch list period, the owner has 15 days after the triggering event to give one, and if none is given interest begins 14 days after that event. A contractor or lower-tier party may withdraw retained amounts by depositing U.S. Treasury obligations, Florida bonds or notes, or insured certificates of deposit. The law applies to written contracts entered into after December 31, 1992 for which a construction lien is authorized, and it sets no maximum percentage. This is Fla. Stat. § 715.12.
How much retainage can be held on private construction in New York?
In New York, retainage on a private construction project with an aggregate cost of $150,000 or more may not exceed five percent of the contract sum and is released no later than thirty days after final approval of the work. By mutual agreement an owner may retain no more than five percent of the contract sum as retainage, and a contractor or subcontractor may retain no more than five percent and never more than the owner actually retains. The owner must release retainage to the contractor no later than thirty days after final approval of the work, and a party that fails to release retainage owes interest at one percent per month. A contract provision requiring retainage above five percent of the contract sum is void and unenforceable. The law covers construction contracts on projects with an aggregate cost of $150,000 or more and excludes public works and smaller residential projects, including one-, two- and three-family homes. This is N.Y. Gen. Bus. Law §§ 756, 756-c, 757.
How much retainage can be held on private construction in Pennsylvania?
In Pennsylvania, the law sets no retainage percentage, but retainage due on final completion is paid within 30 days after final acceptance of the work and passed down to subcontractors within 14 days after it is received. If payments under a construction contract are subject to retainage, amounts retained and due on final completion must be paid within 30 days after final acceptance of the work. A contractor must pay its subcontractors, and each subcontractor its own subcontractors, the full amount due within 14 days after receiving the retainage. On reaching substantial completion of its own scope, a contractor or subcontractor may obtain release of retainage early by posting a maintenance bond for 120% of the amount held. A party that unreasonably withholds acceptance or fails to pay retainage owes interest at 1% per month, and the parties may not waive the act’s provisions by contract unless the act allows it. The act does not apply to improvements of six or fewer residential units under construction at the same time. This is 73 P.S. §§ 509, 503, 505.
How much retainage can be held on private construction in Illinois?
In Illinois, a private construction contract may hold back no more than 10% of any payment before the work is 50% complete and no more than 5% after that, except on single-family homes and buildings of 12 or fewer units. Under the Contractor Prompt Payment Act, a construction contract may provide for retainage of up to 10% of any payment made before 50% of the contract is complete. When the contract is 50% complete, retainage withheld must be reduced so that no more than 5% is held, and no more than 5% of any later payment may be held. The Act does not apply to contracts that require the expenditure of public funds or to contracts for single family residences or multiple family residences with 12 or fewer units in a single building. This is 815 ILCS 603/5(b), 603/20.
How much retainage can be held on private construction in Ohio?
In Ohio, the statute sets no retainage percentage, but a contractor that receives final retainage from the owner pays each subcontractor and supplier its share within ten calendar days, or sooner if their contract says so, or owes eighteen percent interest. A contractor may reduce a subcontractor’s progress payment by any retainage provision in their contract. When the contractor receives final retainage from the owner, it must pay each subcontractor and material supplier its proportion within ten calendar days after receipt, or within any shorter period in their contract, once their work is satisfactory and approved by the owner. A late payment carries interest of eighteen percent per year, and the interest and fee provisions cannot be waived by agreement. The section does not apply to single-, two- or three-family detached dwellings. This is Ohio Rev. Code § 4113.61.
How much retainage can be held on private construction in Georgia?
In Georgia, a contractor must pass retainage through to its subcontractors within 10 days after receiving it from the owner, and the retainage held from a subcontractor cannot exceed the percentage the owner retains on that subcontractor’s work. The owner may withhold a reasonable amount for retainage, but no more than the percentage set in its contract with the contractor; the law sets no maximum percentage and no deadline for the owner’s release. The pass-through duty applies when the subcontractor’s work in place equals 50 percent of its subcontract value, its work is proceeding satisfactorily, and it provides any reasonable assurances of performance the contractor requires. The chapter does not apply to residential improvements of 12 or fewer units. This is O.C.G.A. §§ 13-11-5, 13-11-6, 13-11-10.
How much retainage can be held on private construction in North Carolina?
In North Carolina, a contractor may hold back from a subcontractor only a reasonable retainage no greater than the percentage the owner initially retained, and the statute sets no limit on the owner’s own retainage. A contractor must pay a subcontractor within seven days of receiving each periodic or final payment the full amount received for that subcontractor’s work, but may withhold a reasonable amount for retainage not to exceed the initial percentage retained by the owner. Payments delayed more than seven days bear interest at one percent per month. The chapter does not apply to residential contractors or to residential improvements of 12 or fewer units, among other residential exemptions. This is N.C. Gen. Stat. §§ 22C-4, 22C-3, 22C-5, 22C-6.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Retainage Laws by State for Private Construction — How much retainage may be held on private construction and when it must be released, in each of the 35 jurisdictions with a statute.
Other rules compared across states
- How the interest works in 14 states
- Maximum deposit in 30 states
- Deadline to return the deposit in 49 states
- Notice before entry in 23 states
- Notice before a nonpayment case in 49 states
- Notice to end a tenancy in 46 states
- Notice before a rent increase in 30 states
- Maximum late fee in 17 states
- Grace period before a late fee in 14 states
- Application fee limit in 17 states
- The first step in 22 states
- Time to respond in 22 states
- The rule on lockouts in 22 states
- Cause needed to end a tenancy in 5 states
- Adverse possession period in 51 states
- Rent control in 33 states
- Housing vouchers in 30 states
- Retaliation period in 39 states
- Rent withholding in 19 states
- Repair and deduct in 19 states
- Landlord’s duty to re-rent in 34 states
- Ending the lease early in 39 states
- Holding over in 35 states
- Ending the lease for care in 10 states
- Subletting in 18 states
- Belongings left behind in 43 states
- Carbon monoxide alarms in 28 states
- Electrician license in 45 states
- General contractors in 36 states
- Home improvement contractors in 11 states
- HVAC license in 34 states
- Plumber license in 45 states
- A deed to two or more people in 47 states
- Transfer-on-death deed in 35 states
- Lien waivers in 33 states
- Deadline to file the lien in 51 states
- Payment deadline in 36 states
- State transfer tax in 35 states
- Seller disclosure in 48 states
- Right to cancel in 51 states
- Labor on an appliance repair in 20 states
- Capital improvement in 8 states
- Repair labor on real property in 15 states
- How the contractor is treated in 51 states
Every rule for one state
- Alabama landlord and tenant rules
- Alaska landlord and tenant rules
- Arizona landlord and tenant rules
- Arkansas landlord and tenant rules
- California landlord and tenant rules
- Colorado landlord and tenant rules
- Connecticut landlord and tenant rules
- Delaware landlord and tenant rules
- District of Columbia landlord and tenant rules
- Florida landlord and tenant rules
- Georgia landlord and tenant rules
- Hawaii landlord and tenant rules
- Idaho landlord and tenant rules
- Illinois landlord and tenant rules
- Indiana landlord and tenant rules
- Iowa landlord and tenant rules
- Kansas landlord and tenant rules
- Kentucky landlord and tenant rules
- Louisiana landlord and tenant rules
- Maine landlord and tenant rules
- Maryland landlord and tenant rules
- Massachusetts landlord and tenant rules
- Michigan landlord and tenant rules
- Minnesota landlord and tenant rules
- Mississippi landlord and tenant rules
- Missouri landlord and tenant rules
- Montana landlord and tenant rules
- Nebraska landlord and tenant rules
- Nevada landlord and tenant rules
- New Hampshire landlord and tenant rules
- New Jersey landlord and tenant rules
- New Mexico landlord and tenant rules
- New York landlord and tenant rules
- North Carolina landlord and tenant rules
- North Dakota landlord and tenant rules
- Ohio landlord and tenant rules
- Oklahoma landlord and tenant rules
- Oregon landlord and tenant rules
- Pennsylvania landlord and tenant rules
- Rhode Island landlord and tenant rules
- South Carolina landlord and tenant rules
- South Dakota landlord and tenant rules
- Tennessee landlord and tenant rules
- Texas landlord and tenant rules
- Utah landlord and tenant rules
- Vermont landlord and tenant rules
- Virginia landlord and tenant rules
- Washington landlord and tenant rules
- West Virginia landlord and tenant rules
- Wisconsin landlord and tenant rules
- Wyoming landlord and tenant rules