How much retainage can be held on private construction in Alabama?
In Alabama, retainage on a private construction contract is capped at 10 percent of the work properly done and stored materials, no more may be withheld once the project is 50 percent complete, and the owner must release it within 60 days after the contractor’s work is complete or after substantial completion of the project, whichever occurs first. An owner who withholds more than the law allows owes the contractor interest on the excess at one percent per month, and the same 10 percent and 50 percent limits apply to retainage a contractor holds from its subcontractors. The chapter does not apply to residential homebuilders, residential improvements of 16 or fewer units, contracts of $10,000 or less, or contracts with the state or local governments. This is Ala. Code §§ 8-29-3, 8-29-7.
| What | Alabama |
|---|---|
| Retainage | Capped at 10%, none after 50%; released within 60 days |
What the statute says
“… not more than 10 percent of the estimated amount of work properly done and the value of materials stored on the site or suitably stored and insured off-site, and after 50 percent completion has been accomplished, no further retainage shall be withheld …”
Quoted word for word from the section’s text.
Source
Read the statute in the Code of Alabama (Alabama Legislature): alison.legislature.state.al.us.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Retainage Laws by State for Private Construction — How much retainage may be held on private construction and when it must be released, in each of the 35 jurisdictions with a statute.
Compare this rule in every state
More Alabama rules
- How long does a landlord have to return a security deposit in Alabama?
- How much can a landlord charge for a security deposit in Alabama?
- How many days does a tenant get to pay late rent in Alabama?
- How much notice does a landlord have to give before entering in Alabama?
- How much notice must a landlord give to end a tenancy in Alabama?
- What are squatters’ rights in Alabama?
- Is there rent control in Alabama?
- Can a landlord retaliate against a tenant for complaining in Alabama?
- What happens if a tenant breaks a lease in Alabama?
- What happens when a tenant stays after the lease ends in Alabama?
- What can a landlord do with a tenant’s belongings left behind in Alabama?
- Do HVAC contractors need a license in Alabama?
- Do you need a general contractor license in Alabama?
- Do you need a license to do electrical work in Alabama?
- Do you need a license to work as a plumber in Alabama?
- Does a home improvement contractor need a license or registration in Alabama?
- How does joint tenancy with right of survivorship work in Alabama?
- What does Alabama’s prompt payment law require on private construction?
- What is the deadline to file a mechanic’s lien in Alabama?
- What is the real estate transfer tax in Alabama?
- How long does a homeowner have to cancel a home improvement contract in Alabama?
- Do contractors charge sales tax in Alabama?
- Every Alabama rule on one page
The same question in other states
- Arizona
- California
- Colorado
- Connecticut
- District of Columbia
- Florida
- Georgia
- Idaho
- Illinois
- Kansas
- Kentucky
- Louisiana