How much retainage can be held on private construction in Illinois?

In Illinois, a private construction contract may hold back no more than 10% of any payment before the work is 50% complete and no more than 5% after that, except on single-family homes and buildings of 12 or fewer units. Under the Contractor Prompt Payment Act, a construction contract may provide for retainage of up to 10% of any payment made before 50% of the contract is complete. When the contract is 50% complete, retainage withheld must be reduced so that no more than 5% is held, and no more than 5% of any later payment may be held. The Act does not apply to contracts that require the expenditure of public funds or to contracts for single family residences or multiple family residences with 12 or fewer units in a single building. This is 815 ILCS 603/5(b), 603/20.

WhatIllinois
RetainageCapped at 10%, then 5% once the job is 50% complete

What the statute says

“… may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held …”

Quoted word for word from the section’s text.

Source

815 ILCS 603/5(b), 603/20

Read the statute in the Illinois Compiled Statutes (Illinois General Assembly): ilga.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Illinois rules

The same question in other states

Related