How much retainage can be held on private construction in Kentucky?

In Kentucky, on private construction other than residential, no more than 10% may be held from any payment until the project is 50% complete, retainage held after 51% completion may not exceed 5% of the total contract amount, and it must be released within 30 days after substantial completion. Until 50% of the construction project is complete, a contracting entity, contractor or subcontractor may withhold no more than 10% retainage from any undisputed payment, and retainage held after 51% completion may not be more than 5% of the total contract amount. Within 30 days after substantial completion, the retainage must be released less 200% of the reasonably estimated cost of any uncompleted work, and the contractor must pass subcontractors their proportional shares within 15 business days after receiving it. Retainage not paid when due bears interest at 12% per year. The rule applies to private construction excluding residential construction. This is KRS 371.410, 371.425.

WhatKentucky
Retainage10%, then 5% past 50%; released 30 days after completion

What the statute says

“… may withhold no more than ten percent (10%) retainage from the amount of any undisputed payment due, and retainage held after fifty-one percent (51%) of the construction project has been completed shall not be more than five percent (5%) of the total contract amount …”

Quoted word for word from the section’s text.

Source

KRS 371.410, 371.425

Read the statute in the Kentucky Revised Statutes (Kentucky General Assembly): apps.legislature.ky.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Kentucky rules

The same question in other states

Related