How much retainage can be held on private construction in Kentucky?
In Kentucky, on private construction other than residential, no more than 10% may be held from any payment until the project is 50% complete, retainage held after 51% completion may not exceed 5% of the total contract amount, and it must be released within 30 days after substantial completion. Until 50% of the construction project is complete, a contracting entity, contractor or subcontractor may withhold no more than 10% retainage from any undisputed payment, and retainage held after 51% completion may not be more than 5% of the total contract amount. Within 30 days after substantial completion, the retainage must be released less 200% of the reasonably estimated cost of any uncompleted work, and the contractor must pass subcontractors their proportional shares within 15 business days after receiving it. Retainage not paid when due bears interest at 12% per year. The rule applies to private construction excluding residential construction. This is KRS 371.410, 371.425.
| What | Kentucky |
|---|---|
| Retainage | 10%, then 5% past 50%; released 30 days after completion |
What the statute says
“… may withhold no more than ten percent (10%) retainage from the amount of any undisputed payment due, and retainage held after fifty-one percent (51%) of the construction project has been completed shall not be more than five percent (5%) of the total contract amount …”
Quoted word for word from the section’s text.
Source
Read the statute in the Kentucky Revised Statutes (Kentucky General Assembly): apps.legislature.ky.gov.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Retainage Laws by State for Private Construction — How much retainage may be held on private construction and when it must be released, in each of the 35 jurisdictions with a statute.
Compare this rule in every state
More Kentucky rules
- How many days does a tenant get to pay late rent in Kentucky?
- How much notice does a landlord have to give before entering in Kentucky?
- How much notice must a landlord give to end a tenancy in Kentucky?
- What are squatters’ rights in Kentucky?
- Is there rent control in Kentucky?
- Can a landlord refuse a Section 8 voucher in Kentucky?
- Can a landlord retaliate against a tenant for complaining in Kentucky?
- Can a tenant repair and deduct from rent in Kentucky?
- Can a domestic violence victim end a lease early in Kentucky?
- Can a tenant sublet in Kentucky?
- What happens if a tenant breaks a lease in Kentucky?
- What happens when a tenant stays after the lease ends in Kentucky?
- Do HVAC contractors need a license in Kentucky?
- Do you need a license to do electrical work in Kentucky?
- Do you need a license to work as a plumber in Kentucky?
- How does joint tenancy with right of survivorship work in Kentucky?
- What are the rules for lien waivers in Kentucky?
- What does Kentucky’s prompt payment law require on private construction?
- What is the deadline to file a mechanic’s lien in Kentucky?
- Does a home seller have to disclose the property’s condition in Kentucky?
- What is the real estate transfer tax in Kentucky?
- How long does a homeowner have to cancel a home improvement contract in Kentucky?
- Do contractors charge sales tax in Kentucky?
- Every Kentucky rule on one page
The same question in other states
- Alabama
- Arizona
- California
- Colorado
- Connecticut
- District of Columbia
- Florida
- Georgia
- Idaho
- Illinois
- Kansas
- Louisiana