How much retainage can be held on private construction in the District of Columbia?

In the District of Columbia, retainage that is not in good-faith dispute is an undisputed amount the owner must pay within 7 days after the payment date the contract sets, or, if the contract sets no dates, within 15 days after the earliest of the occupancy permit, the owner taking possession or the contractor’s payment request. A contractor must pay a subcontractor’s undisputed amounts within 7 days after receiving payment for that subcontractor’s work. An owner who pays late owes interest of 1.5 percent per month on the undisputed amount. The chapter applies to private contracts entered into on or after October 1, 2013, and it sets no maximum retainage percentage. This is D.C. Code §§ 27A-101, 27A-102, 27A-103, 27A-104, 27A-106.

WhatDistrict of Columbia
RetainageUndisputed retainage paid within 7 days of contract date

What the statute says

“Undisputed amount" means an amount owed on a contract or a subcontract for which there is no good-faith dispute, including any retainage withheld.”

Quoted word for word from the section’s text.

Source

D.C. Code §§ 27A-101, 27A-102, 27A-103, 27A-104, 27A-106

Read the statute in the Code of the District of Columbia (DC Council): code.dccouncil.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More District of Columbia rules

The same question in other states

Related