How much retainage can be held on private construction in Kansas?

In Kansas, retainage on a private construction contract may not exceed 5% of the contract value unless the owner or contractor decides more is needed to ensure performance, never more than 10%, and the owner must release it within 30 days after substantial completion. Retainage may not exceed 5% of the value of the contract or subcontract unless the owner or contractor determines a higher rate is required to ensure performance, and it may never exceed 10%; no more than 10% may be withheld from any undisputed payment. The owner must release all remaining retainage on any undisputed payment within 30 days after substantial completion, although retainage for work still being performed may be held until 30 days after that work is completed. Unpaid retainage bears interest at 18% per year, and before work begins a contractor or subcontractor may ask for alternate security in place of retainage. The Act does not apply to single family residential housing, multifamily residential housing of four units or less, or public works projects. This is K.S.A. 16-1804, 16-1807.

WhatKansas
Retainage5% cap (10% at most); released 30 days after completion

What the statute says

“Retainage shall not exceed 5% of the value of the contract or subcontract unless the owner or contractor determines that a higher rate of retainage is required to ensure performance of the contract. Retainage, however, shall not exceed 10% of the value of the contract …”

Quoted word for word from the section’s text.

Source

K.S.A. 16-1804, 16-1807

Read the statute in the Kansas Statutes (Kansas Revisor of Statutes): ksrevisor.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Kansas rules

The same question in other states

Related