How much retainage can be held on private construction in Arizona?

In Arizona, a contractor bills for release of retention at substantial completion, the bill is deemed approved 14 days after the owner receives it unless the owner gives written reasons, and the owner pays the retention within seven days after approval unless the contract and plans set a different schedule. The owner may withhold a reasonable amount for retention from each progress payment, and when releasing it may keep back only up to 150 percent of the direct costs it reasonably expects to incur for work left incomplete. A contractor may not withhold more retention from a subcontractor than the owner actually retained on that subcontractor’s work. A late payment carries interest at one and one-half percent a month, and the payment rules do not apply to building a dwelling for an owner-occupant unless the contractor’s bills carry the statutory prompt pay notice. This is A.R.S. §§ 32-1182, 32-1183, 32-1188.

WhatArizona
RetainageReleased 7 days after approval at substantial completion

What the statute says

“Except as provided in subsections C and H of this section, the owner shall pay the retention to the contractor within seven days after the date the billing or estimate for release of retention is certified and approved.”

Quoted word for word from the section’s text.

Source

A.R.S. §§ 32-1182, 32-1183, 32-1188

Read the statute in the Arizona Revised Statutes (Arizona Legislature): azleg.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.