How much retainage can be held on private construction in Arizona?
In Arizona, a contractor bills for release of retention at substantial completion, the bill is deemed approved 14 days after the owner receives it unless the owner gives written reasons, and the owner pays the retention within seven days after approval unless the contract and plans set a different schedule. The owner may withhold a reasonable amount for retention from each progress payment, and when releasing it may keep back only up to 150 percent of the direct costs it reasonably expects to incur for work left incomplete. A contractor may not withhold more retention from a subcontractor than the owner actually retained on that subcontractor’s work. A late payment carries interest at one and one-half percent a month, and the payment rules do not apply to building a dwelling for an owner-occupant unless the contractor’s bills carry the statutory prompt pay notice. This is A.R.S. §§ 32-1182, 32-1183, 32-1188.
| What | Arizona |
|---|---|
| Retainage | Released 7 days after approval at substantial completion |
What the statute says
“Except as provided in subsections C and H of this section, the owner shall pay the retention to the contractor within seven days after the date the billing or estimate for release of retention is certified and approved.”
Quoted word for word from the section’s text.
Source
A.R.S. §§ 32-1182, 32-1183, 32-1188
Read the statute in the Arizona Revised Statutes (Arizona Legislature): azleg.gov.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Retainage Laws by State for Private Construction — How much retainage may be held on private construction and when it must be released, in each of the 35 jurisdictions with a statute.
Compare this rule in every state
More Arizona rules
- How long does a landlord have to return a security deposit in Arizona?
- How much can a landlord charge for a security deposit in Arizona?
- How many days does a tenant get to pay late rent in Arizona?
- How much notice does a landlord have to give before entering in Arizona?
- How much notice does a landlord have to give before raising the rent in Arizona?
- How much notice must a landlord give to end a tenancy in Arizona?
- Can a landlord change the locks to force a tenant out in Arizona?
- How long does a tenant have to respond to an eviction case in Arizona?
- What are squatters’ rights in Arizona?
- What are the steps to evict a tenant for unpaid rent in Arizona?
- Is there rent control in Arizona?
- Can a landlord retaliate against a tenant for complaining in Arizona?
- Can a tenant repair and deduct from rent in Arizona?
- Can a domestic violence victim end a lease early in Arizona?
- What happens if a tenant breaks a lease in Arizona?
- What happens when a tenant stays after the lease ends in Arizona?
- What can a landlord do with a tenant’s belongings left behind in Arizona?
- Do HVAC contractors need a license in Arizona?
- Do you need a general contractor license in Arizona?
- Do you need a license to do electrical work in Arizona?
- Do you need a license to work as a plumber in Arizona?
- Can you use a transfer-on-death deed in Arizona?
- How does joint tenancy with right of survivorship work in Arizona?
- What are the rules for lien waivers in Arizona?
- What does Arizona’s prompt payment law require on private construction?
- What is the deadline to file a mechanic’s lien in Arizona?
- Does a home seller have to disclose the property’s condition in Arizona?
- How long does a homeowner have to cancel a home improvement contract in Arizona?
- Do contractors charge sales tax in Arizona?
- Is a capital improvement exempt from sales tax in Arizona?
- Every Arizona rule on one page
The same question in other states
- Alabama
- California
- Colorado
- Connecticut
- District of Columbia
- Florida
- Georgia
- Idaho
- Illinois
- Kansas
- Kentucky
- Louisiana