How much retainage can be held on private construction in Georgia?

In Georgia, a contractor must pass retainage through to its subcontractors within 10 days after receiving it from the owner, and the retainage held from a subcontractor cannot exceed the percentage the owner retains on that subcontractor’s work. The owner may withhold a reasonable amount for retainage, but no more than the percentage set in its contract with the contractor; the law sets no maximum percentage and no deadline for the owner’s release. The pass-through duty applies when the subcontractor’s work in place equals 50 percent of its subcontract value, its work is proceeding satisfactorily, and it provides any reasonable assurances of performance the contractor requires. The chapter does not apply to residential improvements of 12 or fewer units. This is O.C.G.A. §§ 13-11-5, 13-11-6, 13-11-10.

WhatGeorgia
RetainageSubs’ retainage passed through within 10 days of receipt

What the statute says

“The contractor shall, within ten days from the contractor’s receipt of retainage from the owner, pass through payments to subcontractors and shall reduce each subcontractor’s retainage in the same manner as the contractor’s retainage is reduced by the owner …”

Quoted word for word from the section’s text.

Source

O.C.G.A. §§ 13-11-5, 13-11-6, 13-11-10

Read the statute in the Official Code of Georgia (Georgia General Assembly): legis.ga.gov.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Georgia rules

The same question in other states

Related