How much retainage can be held on private construction in Oregon?

In Oregon, an owner, contractor or subcontractor may withhold as retainage no more than five percent of the contract price of the work completed, and final payment that is late bears interest of one percent a month starting 30 days after the work is completed and accepted. An owner, contractor or subcontractor may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed. Interest of one percent per month runs on the final payment from 30 days after the work is completed and accepted until payment is tendered. A party notified that the work is complete must accept it or list the work still to be done within 15 days, or interest starts 30 days after that period ends. When a contractor pays a subcontractor in full, including retainage, the owner must pay the contractor the matching retainage within 15 days after notice. The rules do not apply when the owner is the United States or the work is paid for with federal money. This is ORS 701.420, 701.410, 701.440.

WhatOregon
RetainageCapped at 5%; 1% a month interest on late final payment

What the statute says

“An owner, contractor or subcontractor may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed.”

Quoted word for word from the section’s text.

Source

ORS 701.420, 701.410, 701.440

Read the statute in the Oregon Revised Statutes (Oregon State Legislature): oregonlegislature.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.