How much retainage can be held on private construction in Montana?

In Montana, retainage on a construction contract may not exceed 5%, a contractor may hold back from a subcontractor no more than the owner holds back from it, and retainage is released on final acceptance of each separately priced portion of the work. The maximum retainage on construction contracts covered by the payment law may not exceed 5%, and the percentage an owner withholds from the contractor is the most the contractor may withhold from a subcontractor. Retainage must be released upon the final acceptance of each portion of work for which a separate price is stated in the contract. The law covers private as well as government owners, but does not apply to residential projects with a total cost of less than $400,000. This is Mont. Code Ann. §§ 28-2-2110, 28-2-2101, 28-2-2107.

WhatMontana
RetainageCapped at 5%; released on acceptance of each priced portion

What the statute says

“The maximum retainage applied to construction contracts subject to the provisions of this part may not exceed 5%.”

Quoted word for word from the section’s text.

Source

Mont. Code Ann. §§ 28-2-2110, 28-2-2101, 28-2-2107

Read the statute in the Montana Code Annotated (Montana Legislature): leg.mt.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Montana rules

The same question in other states

Related