How much retainage can be held on private construction in Nebraska?

In Nebraska, retainage may not exceed 10%, no more than 5% of later progress payments may be held once the work is half complete, and the owner releases retainage within 45 days after substantial completion. An owner, contractor or subcontractor may withhold retainage only up to the amount in the contract, which may not exceed ten percent. Once the scope of work is fifty percent complete and the work conforms to the contract, no more than five percent of any additional progress payment may be withheld, if the contractor or subcontractor gives reasonable assurances of continued performance. The owner must release and pay all retainage within forty-five days after the project, or a designated portion of it, is substantially complete, and a contractor must pay a subcontractor’s retainage within ten days after receiving it. The act does not apply to residential improvements of no more than four units, and the State of Nebraska is not an owner under it. This is Neb. Rev. Stat. §§ 45-1204, 45-1203, 45-1202, 45-1207.

WhatNebraska
RetainageCapped at 10%, 5% after half done; released in 45 days

What the statute says

“For retainage, in an amount not to exceed the amount specified in the applicable contract, which shall not exceed a rate of ten percent.”

Quoted word for word from the section’s text.

Source

Neb. Rev. Stat. §§ 45-1204, 45-1203, 45-1202, 45-1207

Read the statute in the Nebraska Revised Statutes (Nebraska Legislature): nebraskalegislature.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Nebraska rules

The same question in other states

Related