How much retainage can be held on private construction in Massachusetts?

In Massachusetts, on a private project whose prime contract is $3,000,000 or more, retainage may not exceed 5% of any progress payment, and once 60 days have passed after substantial completion a contractor may apply for it and must be paid within 30 days, except on projects of one to four dwelling units. A contract for construction may not include retainage that exceeds 5% of any progress payment. The rule covers contracts on which a lien may be established under chapter 254 for a project whose prime contract has an original price of at least $3,000,000, and it excludes projects containing or designed to contain one to four dwelling units. After 60 days following substantial completion, a person may apply for payment of retainage, and the application must be paid within 30 days, with 7 more days allowed at each lower tier. Amounts withheld from retainage are limited to the value of missing deliverables (no more than 2.5% of the adjusted contract price if no value was agreed), 150% of the reasonable cost to complete or correct work, and the value of claims. A contract provision that waives, limits or subverts the section is void and unenforceable. This is M.G.L. c. 149, § 29F.

WhatMassachusetts
RetainageCapped at 5% of each progress payment ($3M+ projects)

What the statute says

“No contract for construction shall include retainage that exceeds 5 per cent of any progress payment.”

Quoted word for word from the section’s text.

Source

M.G.L. c. 149, § 29F

Read the statute in the General Laws of Massachusetts (Massachusetts Legislature): malegislature.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Massachusetts rules

The same question in other states

Related