How much retainage can be held on private construction in New Mexico?
In New Mexico, an owner, contractor or subcontractor may not retain or hold back amounts owed for work performed, and the balance due is paid ten days after certification of completion. When making payments, an owner, contractor or subcontractor may not retain, withhold, hold back or in any other manner not pay amounts owed for work performed. Construction contracts must provide for payment within twenty-one days after the owner receives an undisputed request for payment, and for payment to subcontractors and suppliers within seven days after the payer receives payment, with interest of one and one-half percent a month on late amounts. Ten days after certification of completion, any amounts remaining due are paid on presentation of a release, a release of lien claims if required, and proof of completion. The act covers private owners as well as local public bodies and state agencies other than the department of transportation, and does not apply to residential property of four or fewer dwelling units. This is N.M. Stat. Ann. §§ 57-28-5, 57-28-8, 57-28-2, 57-28-3.
| What | New Mexico |
|---|---|
| Retainage | No retainage allowed; balance due 10 days after completion |
What the statute says
“When making payments, an owner, contractor or subcontractor shall not retain, withhold, hold back or in any other manner not pay amounts owed for work performed.”
Quoted word for word from the section’s text.
Source
N.M. Stat. Ann. §§ 57-28-5, 57-28-8, 57-28-2, 57-28-3
Read the statute in the New Mexico Statutes (New Mexico Compilation Commission): nmonesource.com.
The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Retainage Laws by State for Private Construction — How much retainage may be held on private construction and when it must be released, in each of the 35 jurisdictions with a statute.
Compare this rule in every state
More New Mexico rules
- Does a landlord have to pay interest on a security deposit in New Mexico?
- How long does a landlord have to return a security deposit in New Mexico?
- How much can a landlord charge for a security deposit in New Mexico?
- How many days does a tenant get to pay late rent in New Mexico?
- How much notice does a landlord have to give before entering in New Mexico?
- How much notice does a landlord have to give before raising the rent in New Mexico?
- How much notice must a landlord give to end a tenancy in New Mexico?
- How much can a landlord charge for a late rent fee in New Mexico?
- What are squatters’ rights in New Mexico?
- Is there rent control in New Mexico?
- Can a landlord retaliate against a tenant for complaining in New Mexico?
- Can a tenant withhold rent for repairs in New Mexico?
- What happens if a tenant breaks a lease in New Mexico?
- What happens when a tenant stays after the lease ends in New Mexico?
- What can a landlord do with a tenant’s belongings left behind in New Mexico?
- Do HVAC contractors need a license in New Mexico?
- Do you need a general contractor license in New Mexico?
- Do you need a license to do electrical work in New Mexico?
- Do you need a license to work as a plumber in New Mexico?
- Can you use a transfer-on-death deed in New Mexico?
- How does joint tenancy with right of survivorship work in New Mexico?
- What does New Mexico’s prompt payment law require on private construction?
- What is the deadline to file a mechanic’s lien in New Mexico?
- Does a home seller have to disclose the property’s condition in New Mexico?
- How long does a homeowner have to cancel a home improvement contract in New Mexico?
- Do contractors charge sales tax in New Mexico?
- Is a capital improvement exempt from sales tax in New Mexico?
- Is appliance repair taxable in New Mexico?
- Is contractor labor taxable in New Mexico?
- Every New Mexico rule on one page
The same question in other states
- Alabama
- Arizona
- California
- Colorado
- Connecticut
- District of Columbia
- Florida
- Georgia
- Idaho
- Illinois
- Kansas
- Kentucky