How much retainage can be held on private construction in New Mexico?

In New Mexico, an owner, contractor or subcontractor may not retain or hold back amounts owed for work performed, and the balance due is paid ten days after certification of completion. When making payments, an owner, contractor or subcontractor may not retain, withhold, hold back or in any other manner not pay amounts owed for work performed. Construction contracts must provide for payment within twenty-one days after the owner receives an undisputed request for payment, and for payment to subcontractors and suppliers within seven days after the payer receives payment, with interest of one and one-half percent a month on late amounts. Ten days after certification of completion, any amounts remaining due are paid on presentation of a release, a release of lien claims if required, and proof of completion. The act covers private owners as well as local public bodies and state agencies other than the department of transportation, and does not apply to residential property of four or fewer dwelling units. This is N.M. Stat. Ann. §§ 57-28-5, 57-28-8, 57-28-2, 57-28-3.

WhatNew Mexico
RetainageNo retainage allowed; balance due 10 days after completion

What the statute says

“When making payments, an owner, contractor or subcontractor shall not retain, withhold, hold back or in any other manner not pay amounts owed for work performed.”

Quoted word for word from the section’s text.

Source

N.M. Stat. Ann. §§ 57-28-5, 57-28-8, 57-28-2, 57-28-3

Read the statute in the New Mexico Statutes (New Mexico Compilation Commission): nmonesource.com.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More New Mexico rules

The same question in other states

Related