How much retainage can be held on private construction in Utah?
In Utah, retainage on a commercial or industrial construction contract may not exceed 5% of any payment or of the total price, is held in an interest-bearing account, and is released within 45 days of the later of the contractor’s billing and occupancy or final acceptance. On a nonresidential commercial or industrial construction contract, retention withheld from any payment may not exceed five percent of the payment, and total retention may not exceed five percent of the total construction price. Retention withheld by an owner must be placed in an interest-bearing account and accounted for separately, with the interest paid for the benefit of the contractor and subcontractors after the project is completed and accepted. Retention and interest must be released on the contractor’s billing statement within 45 days from the latest of the owner’s receipt of the billing statement, the issue of a certificate of occupancy or final acceptance notice, occupancy allowed without a certificate, or the contractor’s acceptance of final pay quantities. A party who knowingly and wrongfully withholds retention owes a charge of 2% per month on that amount, and no party to a construction contract may require another to waive the section. This is Utah Code § 13-8-5.
| What | Utah |
|---|---|
| Retainage | Capped at 5%; due within 45 days of billing or occupancy |
What the statute says
“… the retention proceeds withheld and retained from any payment due under the terms of the construction contract may not exceed 5% of the payment …”
Quoted word for word from the section’s text.
Source
Utah Code § 13-8-5
Read the statute in the Utah Code (Utah Legislature): le.utah.gov.
Checked against the statute on November 15, 2026.
This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.
How Seayora uses this rule
A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.
Guides on this rule
- Retainage Laws by State for Private Construction — How much retainage may be held on private construction and when it must be released, in each of the 35 jurisdictions with a statute.
Compare this rule in every state
More Utah rules
- How long does a landlord have to return a security deposit in Utah?
- How many days does a tenant get to pay late rent in Utah?
- How much notice must a landlord give to end a tenancy in Utah?
- What are squatters’ rights in Utah?
- Is there rent control in Utah?
- Can a landlord refuse a Section 8 voucher in Utah?
- Can a domestic violence victim end a lease early in Utah?
- What happens if a tenant breaks a lease in Utah?
- What happens when a tenant stays after the lease ends in Utah?
- What can a landlord do with a tenant’s belongings left behind in Utah?
- Do HVAC contractors need a license in Utah?
- Do you need a general contractor license in Utah?
- Do you need a license to do electrical work in Utah?
- Do you need a license to work as a plumber in Utah?
- Can you use a transfer-on-death deed in Utah?
- How does joint tenancy with right of survivorship work in Utah?
- What are the rules for lien waivers in Utah?
- What does Utah’s prompt payment law require on private construction?
- What is the deadline to file a mechanic’s lien in Utah?
- Does a home seller have to disclose the property’s condition in Utah?
- How long does a homeowner have to cancel a home improvement contract in Utah?
- Do contractors charge sales tax in Utah?
- Is appliance repair taxable in Utah?
- Every Utah rule on one page
The same question in other states
- Alabama
- Arizona
- California
- Colorado
- Connecticut
- District of Columbia
- Florida
- Georgia
- Idaho
- Illinois
- Kansas
- Kentucky