What are the rules for lien waivers in Virginia?

In Virginia, a contractor, subcontractor or supplier cannot waive or reduce mechanic’s lien rights in a contract signed before any labor, services or materials are furnished, and such a provision is null and void. Any right to file or enforce a mechanics’ lien may be waived in whole or in part at any time by the person entitled to it, except that a general contractor, subcontractor, lower-tier subcontractor or material supplier may not waive or diminish lien rights in a contract in advance of furnishing any labor, services or materials. A provision that waives or diminishes those lien rights in a contract executed before any labor, services or materials are provided is null and void. This is Va. Code § 43-3.

WhatVirginia
Lien waiversAdvance lien waivers in a contract are void
Kind of ruleAdvance or contract waivers are limited

What the statute says

“… a general contractor, subcontractor, lower-tier subcontractor, or material supplier may not waive or diminish his lien rights in a contract in advance of furnishing any labor, services, or materials.”

Quoted word for word from the section’s text.

Source

Va. Code § 43-3

Read the statute in the Code of Virginia (Virginia General Assembly): law.lis.virginia.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Virginia rules

The same question in other states

Related