What are the rules for lien waivers in Florida?

In Florida, a right to claim a construction lien cannot be waived in advance, a waiver covers only labor, services or materials already furnished, and no one may require a lienor to sign a waiver different from the statutory progress-payment and final-payment forms. A lienor who signs a waiver in exchange for a check may condition the waiver on payment of the check. A waiver that is not substantially similar to the statutory forms is still enforceable according to its terms. This is Fla. Stat. § 713.20.

WhatFlorida
Lien waiversStatutory forms; advance waivers are unenforceable
Kind of ruleThe statute prescribes the waiver forms

What the statute says

“A right to claim a lien may not be waived in advance. A lien right may be waived only to the extent of labor, services, or materials furnished.”

Quoted word for word from the section’s text.

Source

Fla. Stat. § 713.20

Read the statute in the Florida Statutes (The Florida Senate): flsenate.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Florida rules

The same question in other states

Related