What are the rules for lien waivers in New Jersey?

In New Jersey, a waiver of construction lien rights is void unless it is given in exchange for payment, and it takes effect only when and to the extent that payment is actually received. Waivers of construction lien rights are against public policy, unlawful and void unless given in consideration for payment for the work, services, materials or equipment provided or to be provided. Such a waiver is effective only upon and to the extent that the payment is actually received. The statute prescribes no waiver form. This is N.J.S.A. 2A:44A-38.

WhatNew Jersey
Lien waiversWaivers void unless given for payment actually received
Kind of ruleAdvance or contract waivers are limited

What the statute says

“Waivers of construction lien rights are against public policy, unlawful, and void, unless given in consideration for payment for the work, services, materials or equipment provided or to be provided …”

Quoted word for word from the section’s text.

Source

N.J.S.A. 2A:44A-38

Read the statute in the New Jersey Statutes (New Jersey Legislature): njleg.state.nj.us.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More New Jersey rules

The same question in other states

Related