What are the rules for lien waivers in Michigan?

In Michigan, nobody may require a lien waiver in advance of work as part of a contract, such a waiver is invalid except to the extent payment was actually made, and waivers must follow the four statutory conditional and unconditional forms. A person may not require, as part of any contract for an improvement, that construction lien rights be waived in advance of work performed, and a waiver obtained as part of such a contract is contrary to public policy and invalid except to the extent payment was actually made to the person giving it. A lien claimant who receives full payment must give the owner, lessee or designee a full unconditional waiver, and one who receives partial payment must give a partial unconditional waiver for the amount received if asked. A partial or full conditional waiver takes effect when the amount shown in it is paid. Waivers must be executed in substantially the statutory formats: partial unconditional, partial conditional, full unconditional and full conditional. On a residential structure, an owner may not rely on a waiver delivered by someone other than the named lien claimant, if that claimant filed or was excused from a notice of furnishing, without first verifying the waiver with the claimant. This is MCL 570.1115.

WhatMichigan
Lien waiversStatutory conditional and unconditional waiver forms
Kind of ruleThe statute prescribes the waiver forms

What the statute says

“A person shall not require, as part of any contract for an improvement, that the right to a construction lien be waived in advance of work performed. A waiver obtained as part of a contract for an improvement is contrary to public policy …”

Quoted word for word from the section’s text.

Source

MCL 570.1115

Read the statute in the Michigan Compiled Laws (Michigan Legislature): legislature.mi.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Michigan rules

The same question in other states

Related