In Tennessee, a contract provision that tries to waive a mechanic’s lien right is void and unenforceable. Any contract provision that purports to waive any right of lien under the mechanics’ lien chapter is void and unenforceable as against the public policy of the state. A person asked by a prime or remote contractor to sign such a contract is to notify the state board for licensing contractors, and the board can revoke the contractor’s license if the waiver provision is not deleted. Accepting a note for all or part of a lien claim does not waive the lien unless expressly agreed in writing. This is Tenn. Code § 66-11-124.

WhatTennessee
Lien waiversContract waivers of lien rights are void
Kind of ruleAdvance or contract waivers are limited

What the statute says

“Any contract provision that purports to waive any right of lien under this chapter is void and unenforceable as against the public policy of this state.”

Quoted word for word from the section’s text.

Source

Tenn. Code § 66-11-124

Read the statute in the Tennessee Code (Tennessee General Assembly): capitol.tn.gov.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.