What are the rules for lien waivers in Nevada?

In Nevada, a contract term that waives or impairs a contractor’s, subcontractor’s or supplier’s lien rights is void, and a waiver is enforceable only on the statute’s conditional or unconditional progress or final payment form. Any term of a contract that attempts to waive or impair the lien rights of a contractor, subcontractor or supplier is void. A written waiver is unenforceable unless the lien claimant signs a waiver and release in the statutory form and, for a conditional waiver, receives the payment it names. The statute sets out four forms: conditional and unconditional waivers upon progress payment and upon final payment, and each unconditional form must carry a notice in type at least as large as the largest type on the document. This is NRS 108.2457.

WhatNevada
Lien waiversStatutory conditional and unconditional forms
Kind of ruleThe statute prescribes the waiver forms

What the statute says

“Any term of a contract that attempts to waive or impair the lien rights of a contractor, subcontractor or supplier is void.”

Quoted word for word from the section’s text.

Source

NRS 108.2457

Read the statute in the Nevada Revised Statutes (Nevada Legislature): leg.state.nv.us.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Nevada rules

The same question in other states

Related