What are the rules for lien waivers in Wisconsin?

In Wisconsin, a contract term requiring a contractor or supplier to waive lien rights before being paid is void, and a claimant may refuse to sign a waiver until paid in full, though a waiver actually signed is binding. A provision in a contract for the improvement of land that requires a person entitled to a construction lien to waive the lien, or a claim against a payment bond, before being paid for the labor, services, materials, plans or specifications is void. A claimant asked for a waiver may refuse to furnish it unless paid in full for the work it covers. A waiver document the claimant actually signs is valid and binding whether or not consideration was paid and whether it was signed before or after the work, it waives all lien rights for the improvement unless it specifically and expressly limits itself to a particular portion of the work, and any ambiguity in it is construed against the signer. This is Wis. Stat. §§ 779.135, 779.05.

WhatWisconsin
Lien waiversContract terms requiring waivers before payment are void
Kind of ruleAdvance or contract waivers are limited

What the statute says

“Provisions requiring any person entitled to a construction lien to waive his or her right to a construction lien or to a claim against a payment bond before he or she has been paid …”

Quoted word for word from the section’s text.

Source

Wis. Stat. §§ 779.135, 779.05

Read the statute in the Wisconsin Statutes (Wisconsin State Legislature): docs.legis.wisconsin.gov.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.