What are the rules for lien waivers in Wyoming?

In Wyoming, a lien waiver is completed in substantially the form the statute sets out, which waives lien rights for payment received to date, keeps rights to retainage and unpaid work, and is acknowledged before a notary. The form for a waiver of lien is to be completed in substantially the form set out in the statute. That form waives and releases lien rights in consideration of the payment received to date, while reserving claims and lien rights for money withheld as retainage, for labor or materials furnished later and for amounts still unpaid, and it ends with an acknowledgment before a notarial officer. The preliminary notice that contractors, subcontractors and materialmen must send the record owner tells the owner to ask for lien waivers when paying, warns that failing to get them may mean paying twice, and attaches a form of lien waiver. This is Wyo. Stat. § 29-10-101.

WhatWyoming
Lien waiversStatutory lien waiver form, acknowledged before a notary
Kind of ruleThe statute prescribes the waiver forms

What the statute says

“The form for waiver of a lien shall be completed in substantially the following form: Note to lien claimant: Signing this form has legal implications.”

Quoted word for word from the section’s text.

Source

Wyo. Stat. § 29-10-101

Read the statute in the Wyoming Statutes (Wyoming Legislature): wyoleg.gov.

The linked sections open Justia’s free copy of the code, because the state’s own site has no stable address for each section.

Checked against the statute on November 15, 2026.

This is a summary of a published statute, not legal advice. Rules change, local ordinances can add to them, and the terms of a specific lease may differ. Check the citation and speak to a lawyer before acting.

How Seayora uses this rule

A contractor on Seayora keeps every job’s dates, its estimate, its invoices and its payments in one record, so the date work was last performed, the date each invoice went out and the amount still owed are on file when a lien or payment deadline is counted.

Guides on this rule

Compare this rule in every state

More Wyoming rules

The same question in other states

Related