Free schedule of values template
A schedule of values breaks a construction contract’s price into line items that add up to the contract sum, so each payment application can bill the share of the work completed. Enter the line items and the percent complete, add any retainage and earlier payments, then print it or download it for Excel.
What a schedule of values should include
- The project, the owner and the contractor.
- Each line item of the work, usually by trade or phase, with its scheduled value.
- Scheduled values that add up to the contract sum.
- The percent of each line completed to date, and the value of that work.
- The retainage held, if the contract provides for it.
- The payments already made, the payment due now and the balance left to finish.
How the payment due is worked out
The value of work completed to date, less the retainage held on it, is what has been earned. Subtract the payments already made on earlier applications, and what is left is the payment due now.
Retainage and prompt payment rules
Many states cap retainage or set a deadline for releasing it, and many set how quickly a payment must be made once it is due. Seayora’s answers by state give each retainage and prompt payment rule with its statute.
The AIA payment forms
AIA Document G702 and G703 are the American Institute of Architects’ payment application and continuation sheet. This template follows the same arithmetic, but it is not an AIA document; use the AIA forms when the contract requires them.
Job costs on Seayora
On Seayora, labor, materials and vendor costs are tracked against each job or capital project, and invoices take online payment and post to the books when they are paid.
Frequently asked questions
What is a schedule of values in construction?
A breakdown of the contract price into line items that add up to the contract sum, used to bill progress payments by the share of each line completed.
What does SOV mean in construction?
SOV stands for schedule of values: the line-by-line breakdown of a contract’s price used for progress billing.
How is retainage calculated on a payment application?
As a percentage of the value of work completed to date, at the rate the contract sets. It is held back until the contract and any state retainage law say it must be released.