Florida Notice of Commencement: When It Is Required and How to File

Florida’s notice of commencement, Fla. Stat. § 713.13: when an owner must record and post one, what it contains, the $2,500 exemption and when it expires.

By Seayora Editorial Team · Published · Facts checked · 5 min read

Short answer: Before work starts on most Florida improvements, the owner records a notice of commencement with the county clerk and posts a copy at the job site, before the first inspection. It names the property, the owner, the contractor and any bond, lender and designee, and it expires one year after recording unless it states a later date; payments made after it expires are improper and can mean paying twice. A job whose direct contract price is $2,500 or less is exempt (Fla. Stat. §§ 713.13, 713.02(5)).

Key takeaways

  • The owner signs it, records it with the clerk and posts a copy at the site; no one else may sign in the owner’s place.
  • It must be recorded and posted before the first inspection, and above a $5,000 direct contract the building department needs a copy before it will approve later inspections.
  • It is void if work does not start within 90 days of recording, and it expires one year after recording unless it states a later date.
  • An improvement with a direct contract price of $2,500 or less is exempt.

What is a notice of commencement?

A notice of commencement is a short recorded document that tells everyone working on a Florida job — subcontractors, suppliers and lenders — who owns the property, who the contractor is and where to send their notices. Under Fla. Stat. § 713.13, the owner or the owner’s authorized agent records it in the clerk’s office before actually starting an improvement, and posts at the job site either a certified copy or a notarized statement that it has been filed for recording, with a copy. Recording it is not a lien and does not cloud the title; it gives notice that liens may be recorded and sets their priority.

When is a notice of commencement required?

For every improvement to real property except one exempt under § 713.02(5): an improvement whose direct contract price is $2,500 or less. It is required again when work resumes after a default or abandonment. The form in the statute warns that the notice must be recorded and posted on the site of the improvement before the first inspection.

The building department’s $5,000 rule

When the direct contract is greater than $5,000, the building department must require a copy of the recorded notice before the first inspection, and it may not perform or approve later inspections until the copy is filed (§ 713.135(1)(e)). It may not make recording a condition of issuing the permit. These permit-office rules do not apply to a direct contract to repair or replace an existing heating or air-conditioning system for less than $15,000; the notice itself is still governed by § 713.13.

What the notice must contain

  • A description of the property: its legal description, and the street address and tax folio number if available.
  • A general description of the improvement.
  • The owner’s name and address and interest in the property, and the fee simple titleholder’s name and address if different. A tenant who contracts for the work is listed as the owner, with a statement that the interest is a leasehold.
  • The contractor’s name and address.
  • The surety’s name and address and the bond amount, if there is a payment bond; a copy of the bond must be attached when the notice is recorded.
  • The construction lender’s name and address, if any.
  • Any person in Florida the owner designates to receive notices, and anyone else the owner designates to receive copies of lienors’ notices.
  • The expiration date, which is one year after recording unless the notice states a later one.

The statute prints the form the notice must substantially follow, ending with the owner’s signature and a notary’s acknowledgment, and a building department must accept a recorded notice in that form (§ 713.13(1)(d), (h)). Seayora’s free Florida notice of commencement form fills in that form for you to print, sign before a notary and record.

Who signs it

The owner must sign it, and no one else may sign in the owner’s place (§ 713.13(1)(g)); for a company, the form provides for an authorized officer, director, partner or manager. A construction lender must record the notice before disbursing any construction funds to the contractor, but posting it at the site remains the owner’s job (§ 713.13(7)).

How long it lasts

The notice is void if the improvement does not actually start within 90 days after it is recorded (§ 713.13(2)). Unless it states otherwise, it stops being effective one year after recording (§ 713.13(6)), and if the contract allows more than a year to finish, the notice must say it is effective for one year plus the extra time (§ 713.13(1)(c)). A notice can be amended within its effective period to extend it or correct it, but changing contractors takes a new notice (§ 713.13(5)).

Why it matters: paying twice

Payments the owner makes after the notice expires are improper payments, and the warning printed on the form says they “can result in your paying twice for improvements to your property” (§ 713.13(1)(c), (d)). Before the notice expires on a long job, record an amended notice extending it.

What it means for contractors and suppliers

The notice of commencement is where a subcontractor or supplier finds the owner, the property description and any designee for the Notice to Owner that must be served before, or within 45 days after, starting to furnish work (§ 713.06(2)(a)). Ask for a copy before starting, and record the date you first furnished labor or materials on every job. Seayora’s guide to mechanics lien notice deadlines covers the Notice to Owner and the deadline to record a lien.

Frequently asked questions

Who files the notice of commencement in Florida?

The owner or the owner’s authorized agent records it with the county clerk, and the owner must sign it. A construction lender must record it before disbursing construction funds to the contractor, but posting a copy at the job site stays the owner’s responsibility (Fla. Stat. § 713.13).

Do I need a notice of commencement for a small job in Florida?

Not when the direct contract price is $2,500 or less (Fla. Stat. § 713.02(5)). Above that it is required, and when the direct contract is more than $5,000 the building department must have a copy before the first inspection, except for a heating or air-conditioning repair or replacement under $15,000 (§ 713.135).

How long is a Florida notice of commencement good for?

One year after it is recorded, unless it states a later date, and it is void if work does not start within 90 days of recording (Fla. Stat. § 713.13(2), (6)).

Does a Florida notice of commencement have to be notarized?

The form the statute prints ends with a notary’s acknowledgment of the owner’s signature, made in person or by online notarization (Fla. Stat. § 713.13(1)(d)).

State-by-state rules

Sources

  1. Florida Statutes § 713.13, Notice of commencement, The Florida Legislature
  2. Florida Statutes § 713.02, Types of lienors and exemptions, The Florida Legislature
  3. Florida Statutes § 713.135, Notice of commencement and applicability of lien, The Florida Legislature
  4. Florida Statutes § 713.06, Liens of persons not in privity; proper payments, The Florida Legislature

How Seayora helps

Contractor invoicing: Invoices whose payments are recorded with their dates, so every payment on a Florida job is on the record.

This article is general information, not legal advice. Landlord-tenant law varies by state and city and changes often, so check the current rule for your property and talk to an attorney before acting on a dispute.