What Is a Change Order? Meaning, What to Include and an Example (2026)
What a change order is in construction and home repair, what it should include, how it is priced, approved and billed, with a filled-in example.
By Seayora Editorial Team · Published · Facts checked · 4 min read
Short answer: A change order is a written agreement to change the work after a job has started or a contract has been signed: extra work, less work, a different material or a new schedule. It describes the change, its price or credit, and any effect on the completion date, and the customer approves it, ideally with a signature, before the work is done. Approved change orders are then billed with the job’s invoice, so nobody is surprised by the final bill.
Key takeaways
- Write the change, its price and its effect on the schedule before doing the work.
- Get the customer’s approval in writing; if they agree by phone, record how and when.
- A credit for work removed is a change order too, with a negative price.
- Bill every approved change order once, on the job’s invoice or on its own.
What is a change order in construction?
A change order modifies a job that is already agreed. Most construction and home improvement work starts from an estimate or a contract with a fixed scope and price. When the scope changes, the change order records exactly what is different, what it costs and how it affects the schedule, and the customer’s approval turns it into part of the agreement. It protects both sides: the customer is not billed for work they never agreed to, and the contractor is paid for the extra work they did.
When do you need a change order?
- Hidden conditions: rotted subfloor under a cabinet, corroded valves behind a wall, a roof deck that needs replacing.
- The customer asks for more: another outlet, a different tile, an extra room painted.
- A material changes: a substitution because something is unavailable, or a price that has moved.
- Work is taken out: the customer keeps an existing fixture, which becomes a credit.
- The schedule changes: added days for extra work, or a delay the customer causes.
What should a change order include?
| Part | Example |
|---|---|
| The job and the customer | Kitchen remodel, 14 Elm Street |
| A number | Change order 2 |
| What is changing | Replace rotted subfloor under the sink base |
| Why | Found when the old cabinets came out |
| Lines with quantity and price | 24 sq ft at $14.00 |
| Any credit | Customer keeps the existing faucet: −$120.00 |
| Effect on the schedule | One more day |
| Approval | The customer’s name, signature and the date |
What does a change order look like? An example
| Line | Quantity | Price | Amount |
|---|---|---|---|
| Remove and replace subfloor (sq ft) | 24 | $14.00 | $336.00 |
| Moisture barrier and fasteners | 1 | $45.00 | $45.00 |
| Credit: customer keeps the existing faucet | 1 | −$120.00 | −$120.00 |
| Total before tax | $261.00 |
The change adds one day to the schedule. The customer approves it before the subfloor is replaced, and the $261.00 is added to the final invoice, with sales tax worked out there where it applies.
Who approves a change order, and when?
The contractor writes it and the customer approves it, before the changed work begins. A signature is the clearest proof; if the customer agrees by phone, text or email, record how and when they agreed. Once a change order has been sent, do not edit it: withdraw it, change it and send it again, so what the customer approved is always what they saw. Many construction contracts say how changes must be made, so follow your contract’s own process.
How is a change order billed?
An approved change order is billed like the rest of the job: added line by line to the job’s invoice, or invoiced on its own if the main invoice has already gone out. Each change order should be billed exactly once. Keep it with the job’s photos and notes, because when a customer questions an invoice, the signed change order answers whether the extra work was authorized.
What is the difference between a change order and a new estimate?
A change order modifies a job already under way and belongs to it. Separate work that could stand alone, such as a second bathroom after the kitchen is finished, is better quoted as a new estimate, which becomes its own job. See our guide to estimating software for contractors.
How does Seayora handle change orders?
In Seayora a change order starts from the job and is numbered on it. You add lines with quantity and price, a credit as a negative line, the reason and any change to the schedule, and save it as a draft. Send to customer emails a link to it on their portal, where they approve it by typing their name and checking a box, which is recorded with the time and their device, or decline it with a reason. A sent change order cannot be edited until you withdraw it. If the customer answers in person or by phone, you record how. When you invoice the job, every approved change order not yet billed is added line by line, and each is billed once. Totals are before sales tax, which the invoice adds. For a job you are not running in Seayora, the free change order template prints the same document. There is no subscription and no per-seat charge: Seayora takes 3.8% only when you are paid for a completed job through it, and a listing in Find a pro is free.
Frequently asked questions
Does a change order need a signature?
It should be approved in writing before the work, and a signature is the clearest proof. If a customer approves by phone or text, record how and when; many contracts require changes to be made in writing.
Can a change order reduce the price?
Yes. Work taken out of the job is a credit, written as a line with a negative price.
Does a change order include sales tax?
It depends on the job and the state. In Seayora a change order’s total is before tax, and the invoice adds sales tax line by line where it applies.
Who writes the change order?
Usually the contractor, who prices the change; the customer reviews and approves it.
How Seayora helps
Contracts and change orders: Change orders the customer approves and signs on their portal, billed once on the job’s invoice.
How we write and check these guides: editorial standards.
Related on Seayora
- Painting Contractor Software (2026): Estimates, Crews, Invoices — Guide. What painting contractor software should do: estimates with options, deposits, crews, a painting checklist, change orders, punch lists and invoicing.
- Roofing Software in 2026: Estimates, Photos, Crews and Billing — Guide. What roofing software should do for a roofing contractor: inspections with photos, estimates with options, crews, change orders, deposits and invoicing.
- What Is a Work Order? Meaning, What to Include and How It Works (2026) — Guide. What a work order is for landlords, property managers and contractors, how it differs from a maintenance request and a purchase order, and what to include.
- Electrical Contractor Software: Estimates to Payment — Feature. Free electrical contractor software: estimates with materials, change orders, crews, license reminders, job costing and invoices paid online.
- Painting Business Software: Estimates and Invoicing — Feature. Free painting business software: estimates by area with materials and your cost, change orders, crews, scheduling, photos and invoices paid online.
- Writing Estimates — Documentation. How to keep your clients and their service addresses, build an accurate estimate with hours, your costs and discounts, get it approved inside your team, send it with Approve and Decline buttons and the PDF, forward it, answer your customer’s replies, plan and get reminded about the site visit, and turn an accepted estimate into an invoice or scheduled work.